Michigan 765-kV Feasibility Study

AEP and ITC Transmission complete technical study on benefits of expanding 765-kV transmission into Michigan
In Nov. 2006, AEP signed a memorandum of understanding (MOU) with ITC Transmission, a subsidiary of ITC Holdings Corp. (ITC), to perform a technical study to evaluate the feasibility of extending AEP’s 765-kilovolt (kV) transmission infrastructure into, and through, the state of Michigan.

The study explores the merits and benefits of building a 765-kV transmission network in Michigan’s Lower Peninsula that would link to AEP’s 765-kV transmission system in the Midwest.

The Proposed 765 kV Transmission Infrastructure Expansion study (PDF : 2.06 MB: get viewer) is being shared with the Midwest ISO (MISO) and the Michigan Public Service Commission’s (MPSC) 21st Century Energy Planning team.

The study proposes that the existing 765 kV transmission system that extends into the southwest corner of the Lower Peninsula of Michigan be extended east across Michigan and south down to the existing 765 kV infrastructure in Ohio.

The extension would consist of three segments comprising approximately 700 miles of transmission infrastructure.  The study estimates the cost of the project at approximately $2.6 billion in 2007 dollars. The entire 765 kV project would be expected to take approximately eight years to build assuming three years to site and acquire rights-of-way and five years to construct.

The MOU signed with ITC Transmission does not include provisions to build or operate transmission. Any future activities regarding Michigan transmission will be determined after the completion of the study.

Also see:

Welcome to About Us
 
Return to the home page
Mission, Vision, & Values
Facts at a glance
AEP leadership
History of AEP
Regulated utility operations
Power plants and other assets
IGCC
Transmission: The Next Interstate System
 
- AEP Interstate Project (I-765)
- Electric Transmission Texas LLC
- Michigan 765-kV Feasibility Study
- SPP Investment Potential
- Transmission “Firsts”
- Wyoming-Jacksons Ferry 765-kV Project
- Transmission Questions & Answers
   
AEP Web sites
Advertising
Local issues
Economic development
Suppliers
Doing business with AEP
Coal combustion products
Required Internet postings
 
back to top Click here to go back to the top of the page
Home
Investors | Newsroom
Corporate Citizenship
Careers | About Us | Contact Us
Use of this site constitutes acceptance of the AEP Terms and Conditions.
American Electric Power. All Rights Reserved.
 Advanced Search | Site Map | A-Z Index