River Flows for Hydro Plants

You may track, on an hourly basis, water levels and flows of the recreational rivers and lakes near AEP's hydroelectric facilities. See a map of our plant locations.

Explanation of terms

  • The "Forebay" and "Tailwater" numbers show the feet above sea level of the water levels immediately upstream and downstream from our plants.
  • "Tailwater Flow" is the hourly average of the river flow just downstream of the plants, measured in cubic feet per second.

Updated 24-APR-2024 18:35 EDT

New River Flows & Forecasts

Water release information for AEP's Claytor, Buck, and Byllesby hydro dams is updated every fifteen minutes. PLEASE NOTE: Forecast information is estimated. Water travel times may be affected by water conditions, precipitation in the watershed and other factors

Most Recent Conditions

Project Normal Full Pond Forebay Actual (Feet) Tail Water (Feet) Tail Water (CFS)
Buck 2003.40 2003.07 1961.73 2273
Byllesby 2079.20 2078.71 2023.04 2218
Claytor 1846.00 1845.50 1731.61 3007

See plant-specific notices below.

New River - Downstream Forecasts

Forecast information shows water release information from the Claytor dam, delayed to account for the average time it takes the released water to reach particular points downstream. Water travel times may be affected by water conditions, precipitation in the watershed and other factors.

Kanawha River

Project Normal Full Pond Forebay Actual (Feet) Tail Water (Feet) Tail Water (CFS)
London 614.00 614.01 590.79 5113
Marmet 590.00 589.98 566.89 6059
Winfield 566.00 566.20 539.70 3976

See plant-specific notices below.

Roanoke River

Project Normal Full Pond Forebay Actual (Feet) Tail Water (Feet) Tail Water (CFS)
Leesville 613.00.00 604.08 532.57 913
Niagara 885.00 884.85
Smith Mountain 795.00 794.69 604.15

See plant-specific notices below.

Saint Joseph River

Project Normal Full Pond Forebay Actual (Feet) Tail Water (Feet) Tail Water (CFS)
Berrien Springs 623.50 623.55 599.28 6173
Buchanan summer: 637.50
winter: 637.20
637.50 625.69 4496
Constantine 782.90 782.98 771.98
Elkhart 741.50
winter: 739.50
739.54 722.34
Mottville summer: 770.40
winter: 770.00
770.42 759.92 2550
Twin Branch 717.10 716.93 696.70 4568

See plant-specific notices below.

Plant-Specific Notices

As of 05:00 this morning, Wednesday April 24, 2024, inflow to the Smith Mountain Project was 1030 CFS and the discharge from Leesville was 993 CFS. The adjusted reservoir elevation was 795.2 ft. The flow rate at the USGS Gauge at Brookneal was 1620 CFS, Stage 5.31 ft. and at Altavista 1270 CFS, Stage 2.61 ft.