Regulatory Activity Underway AEP Transmission Companies PJM OATT and SPP OATT filings
Docket Number ER10-355-000
Overview

On December 1, 2009 AEPSC made a filing with FERC for a formula rate to establish an up-to-date revenue requirement for transmission services over the facilities of the American Electric Power Transmission Companies (AEPTCo) subsidiaries under the PJM Open Access Transmission Tariff and under the SPP Open Access Transmission Tariff as applicable to implement a transmission cost of service formula rate. February 1, 2010 was requested as the effective date for initial rates for the formula rate.

Procedural Schedule TBD
Key Components Requested ROE: 12.1% including a 50 basis point rider in PJM, 11.9% including a 50 basis point rider in SPP.
Requested Capital Structure: 50/50
Requested Rate Base: $31.8MM for subsidiaries in PJM and $5.6MM for subsidiaries in SPP.
Requested Revenue Requirement: $4.3MM for the subsidiaries in PJM and $0.8MM for the subsidiaries in SPP.