River Flows for Hydro Plants

You may track, on an hourly basis, water levels and flows of the recreational rivers and lakes near AEP's hydroelectric facilities. See a map of our plant locations.

Explanation of Terms

  • The "Forebay" and "Tailwater" numbers show the feet above sea level of the water levels immediately upstream and downstream from our plants.
  • "Tailwater Flow" is the hourly average of the river flow just downstream of the plants, measured in cubic feet per second.

New River Flows & Forecasts

Water release information for AEP's Claytor, Buck, and Byllesby hydro dams is updated every fifteen minutes. Forecast information is estimated. Water travel times may be affected by water conditions, precipitation in the watershed and other factors.

Most Recent Conditions

ProjectNormal Full PondForebay Actual (Feet)Tail Water (Feet)Tail Water (CFS)
Buck2003.402002.901960.911810
Byllesby2079.202078.76-1775
Claytor1846.001845.521731.023087
See plant-specific notices below. Data last updated on Mar 22 2026, 12:04 AM EST. Tail water (cfs) is last hour average.
Byllesby tail water elevation temporarily unavailable.

Downstream Forecasts

Forecast information shows water release information from the Claytor Dam, delayed to account for the average time it takes the released water to reach particular points downstream. Water travel times may be affected by water conditions, precipitation in the watershed and other factors.

Kanawha River

ProjectNormal Full PondForebay Actual (Feet)Tail Water (Feet)Tail Water (CFS)
London614.00613.86592.2710171
Marmet590.00589.90569.846717
Winfield566.00566.40541.787751
See plant-specific notices below. Data last updated on Mar 22 2026, 12:04 AM EST. Tail water (cfs) is last hour average.

Roanoke River

ProjectNormal Full PondForebay Actual (Feet)Tail Water (Feet)Tail Water (CFS)
Niagara885.00885.54
Smith Mountain795.00792.82606.26
Leesville613.00.00608.93534.49547
See plant-specific notices below. Data last updated on Mar 22 2026, 12:04 AM EST. Tail water (cfs) is last hour average.

Saint Joseph River

ProjectNormal Full PondForebay Actual (Feet)Tail Water (Feet)Tail Water (CFS)
Constantine782.90783.54771.99
MottvilleSummer: 770.40
Winter: 770.00
770.44760.062750
Elkhart741.50
winter: 739.50
741.55723.90
Twin Branch717.10716.91696.885569
BuchananSummer: 637.50
Winter: 637.00
637.48626.296349
Berrien Springs623.50623.54599.747734
See plant-specific notices below. Data last updated on Mar 22 2026, 12:04 AM EST. Tail water (cfs) is last hour average.

Plant–Specific Notices

As of 05:00 this morning, Saturday March 21, 2026, inflow to the Smith Mountain Project was 1253 CFS and the discharge from Leesville was 463 CFS. The adjusted reservoir elevations was 794.0 ft. The flow rate at the USGS Gauge at Brookneal was 1020 CFS, Stage 4.72 ft. and at Altavista 643 CFS, Stage 1.88 ft.